JAPAN · POLICY · DATA CENTER LOCATION

Japan's GX Strategic Regions for data center clusters:
the 9 designated regions and how they were chosen.

Japan has designated GX Strategic Regions where gigawatt-class data center clusters are to be built. This page sets out which regions were designated, the selection criteria, the support, and what it means for data center operators, based on the government's published material.

By Wallingford Co., Ltd. · Updated

Discuss your project

Key points

The data center cluster type of Japan's GX Strategic Regions (GX戦略地域) is a national programme that selects regions to become gigawatt-class data center clusters over roughly the next ten years, and provides support such as advance grid build-out together with regulatory and institutional reform. On 11 September 2026 the Ministry of Economy, Trade and Industry (METI) designated the first round: 9 regions (10 sites).

  • Prefectures apply. Data center operators take part by joining a local government's plan.
  • The nine designated regions are Hokkaido, Akita, Miyagi, Tochigi, Ibaraki, Toyama, Kagawa, Fukuoka and Kagoshima. Being located away from the existing clusters (the Tokyo and Osaka areas) is one of the selection criteria.
  • Support centres on building out the power grid and telecom infrastructure in advance. Support for the construction cost of ordinary data centers is limited to projects that meet set conditions.
  • Designation does not guarantee any individual operator a power supply or permits. Outlines of each region's plan are to be published later.

This page is based on METI's policy page, METI press releases and the Cabinet Secretariat's interim report. The content was checked against the Japanese originals on 20 November 2026. The Japanese version of this page is GX戦略地域(データセンター集積型)とは.

What the GX Strategic Region programme is

The GX Strategic Region programme is designed to create new industrial clusters around industrial assets such as industrial complexes (kombinato) and around decarbonised power sources, which are unevenly distributed across Japan. According to METI, it was established in August 2025 as a concrete measure under the GX2040 Vision, which the Cabinet approved in February 2025. GX stands for green transformation.

Types under the GX Strategic Region programme (per METI's policy page; English names are our translations)
TypeWhat it coversWho is selected
1. Industrial complex regeneration type (コンビナート等再生型)Using industrial complexes to form new clusters of GX-related industriesRegions
2. Data center cluster type (データセンター集積型)Forming gigawatt-class data center clusters over roughly the next ten yearsRegions
3. Decarbonised power utilisation type (脱炭素電源活用型)Developing industrial parks that use decarbonised power (renewables and nuclear)Regions
4. Decarbonised power regional contribution type (脱炭素電源地域貢献型)Backing capital investment by businesses that use decarbonised power and contribute to the areas hosting those power sources (GX Regional Co-creation Subsidy, GX地域共創補助金)Businesses

For types 1 to 3, local governments and companies draw up plans, and the national government selects regions and provides support together with regulatory and institutional reform. The call for applications describes the data center cluster type as initiatives and plans to form data center clusters, and industrial clusters built around them, taking into account the efficiency of power and telecom infrastructure development.

Timeline so far

Timeline of the GX Strategic Regions (data center cluster type)
WhenWhat happened
February 2025The Cabinet approves the GX2040 Vision
June 2025The Public-Private Council on Watt-Bit Collaboration (ワット・ビット連携官民懇談会) of MIC and METI publishes its Report 1.0, setting out a policy of creating several gigawatt-class data center cluster sites
August 2025The GX Strategic Region programme is established. Local governments and businesses submit 199 proposals in total, 90 of them for the data center cluster type
22 December 2025The Cabinet Secretariat's GX Implementation Promotion Office publishes its interim report (selection criteria and support)
23 December 2025 – 13 February 2026Call for applications for regional selection
24 April 2026Promising regions (those that passed the first screening) are selected: 9 regions for the data center cluster type, with only prefecture names published
11 September 2026First round of GX Strategic Regions designated: 9 regions (10 sites) for the data center cluster type

In the April 2026 selection of promising regions, the data center cluster type was screened at municipality level, but only prefecture names were published in order to prevent moves such as speculative holding of land or power capacity. The site names were published with the designation in September.

The 9 designated regions (10 sites)

According to METI's press release, the following 9 regions (10 sites) were designated as the first round of data center cluster GX Strategic Regions. The second column shows the sites where a gigawatt-class data center cluster is to be formed.

GX Strategic Regions, first round — data center cluster type (designated 11 September 2026)
Applicant (prefecture)Sites where the cluster is to be formed
Hokkaido (北海道)Ishikari City and Tomakomai City (石狩市、苫小牧市) — a gigawatt-class cluster at each of the two sites
Akita Prefecture (秋田県)Akita City (秋田市)
Miyagi Prefecture (宮城県)Tomiya City (富谷市)
Tochigi Prefecture (栃木県)Yaita City (矢板市)
Ibaraki Prefecture (茨城県)Joso City / Tsukuba City (常総市/つくば市)
Toyama Prefecture (富山県)Nanto City (南砺市)
Kagawa Prefecture (香川県)Ayagawa Town / Sakaide City / Marugame City (綾川町/坂出市/丸亀市)
Fukuoka Prefecture (福岡県)Kitakyushu City / Nogata City / Kurate Town (北九州市/直方市/鞍手町)
Kagoshima Prefecture (鹿児島県)Satsumasendai City (薩摩川内市)

METI states that it attached conditions to the designation, including steady implementation of the plans and securing coexistence with local communities. Outlines of each region's plan are to be published later; the policy page as updated on 10 November 2026 says the same. The power capacity and development timing of individual sites cannot be confirmed from the published material.

Selection criteria: power, telecoms, land and community

The Cabinet Secretariat's interim report sets out the selection criteria for the data center cluster type and says regions are selected by evaluating them as a whole. The main criteria are as follows.

Main selection criteria for the data center cluster type (per the interim report)
AspectCriteria
PowerPotential to expand to gigawatt class in future (for example, gigawatt-class supply possible in about ten years), how quickly power supply can ramp up, supply voltage suited to data center operators, spare supply capacity today, and low development cost
TelecomsPotential to secure underground and redundant telecom networks near the candidate land, and potential to secure international connectivity
Disaster riskAbility to secure an area with stable ground and low disaster risk
LandProspect of providing industrial land of roughly 30 ha or more (saleable area) for the cluster as a whole within a 10 km radius; where several plots are combined, 10 ha or more per plot is desirable
Water and transportAvailability of water, including industrial water, and good transport access
DispersalLocation away from the existing data center clusters
Operator needsCommunication with data center operators, and a plan that matches their needs
Decarbonised powerA local government that is keen to use decarbonised power
CommunityMeasures for coexistence with the local area, such as cooperation from the local government in gaining neighbours' understanding

These criteria are written for gigawatt-class clusters, but the same aspects — spare power capacity, telecom redundancy, disaster risk, water and coexistence with the community — are the ones used to compare candidate sites for a small data center. Our site and power checklist covers them for projects below 2 MW.

Support for designated regions

METI says it will back the formation of industrial clusters in designated GX Strategic Regions by supporting capital investment, building out the power grid in advance, and regulatory and institutional reform. The Cabinet Secretariat's interim report lists the following support for the data center cluster type, and notes that the measures are finalised only after the budget process.

  • Advance, planned build-out of the power grid: building the grid ahead of demand, including through loans to general transmission and distribution operators before the facilities start operating.
  • Support for telecom infrastructure and for demonstration projects.
  • Development support for data centers that meet set conditions: those aimed at regional dispersal (requirements include being located outside the Tokyo and Osaka areas) and those using 100% decarbonised power (requirements include contributing to the areas hosting decarbonised power sources).
  • Financial support: equity investment and debt guarantees by the GX Acceleration Agency (GX推進機構) and others.
  • Measures to secure industrial water.
  • Regulatory and institutional reform, coordinated with the National Strategic Special Zone system.

As background, the interim report points out that power infrastructure is tight as data center demand surges, and that there are cases where grid connection takes more than ten years. Support is limited to the selected cluster areas within the selected prefectures.

What it means for data center operators

The points below are our own reading of the published material.

  1. Operators take part through a local government's plan. The unit of selection is the prefecture, and an application may also be filed jointly with municipalities or private businesses. If you are considering a site in a designated region, ask the applicant local government about the content of its plan.
  2. Designation does not guarantee an individual operator a power supply. Power is decided through an application to and consultation with the utility. Our planning guide explains the application steps.
  3. Construction support is conditional. The interim report notes that ordinary data center construction is already moving forward on a commercial basis, and limits support to data centers that contribute to regional dispersal and those that use 100% decarbonised power while contributing to the areas hosting decarbonised power sources.
  4. Watch for the plan outlines. Outlines of each region's plan are to be published later. Confirm the scale and timing of each site from that material once it is released.

The data center cluster type is about gigawatt-class clusters. It differs in scale and approach from the small projects Wallingford supports, where the facility's total incoming power is below 2 MW. For a small project, the starting point is to confirm the power outlook site by site in places where the existing grid has spare capacity.

Background: Watt-Bit Collaboration

The data center cluster type rests on the idea of Watt-Bit Collaboration (ワット・ビット連携): developing power and telecom infrastructure together. The Ministry of Internal Affairs and Communications (MIC) and METI convened the Public-Private Council on Watt-Bit Collaboration as a forum for public and private stakeholders, and published Report 1.0 in June 2025.

Report 1.0 sets out the following directions for data center location.

  • Encourage data centers to locate in areas where the grid has spare capacity and power can be supplied early, by improving disclosure such as expanding the Welcome Zone Maps (ウェルカムゾーンマップ) published by general transmission and distribution operators.
  • In addition to the existing clusters, aim to select regions and build out power and telecom infrastructure in advance, so as to create several data center cluster sites of gigawatt class each.
  • Continue to encourage the regional dispersal of data centers.
  • Review grid connection rules so that power reaches the businesses that genuinely need it quickly.

Report 1.0 also asks data center operators, in addition to complying with the relevant laws, to work carefully at building consensus, for example by creating opportunities to explain their construction plans and the effects on the surrounding environment to the host community. For developments at municipal level, see Tokyo's data center guideline.

How Wallingford helps

Wallingford Co., Ltd. supports projects below 2 MW of total incoming power with comparison of candidate sites, support for utility consultations and applications, and comparison of design and construction options. Wallingford is not involved in any GX Strategic Region application or designation; this page is a general explanation based on published material.

The programme may be updated. When planning, check METI's policy page and the latest material published by each local government. We do not guarantee land availability, power supply, permits, the award of subsidies or completion dates.

Frequently asked questions

What is a GX Strategic Region in Japan?

A GX Strategic Region (GX戦略地域) is a region selected by the Japanese government to build industrial clusters around assets such as industrial complexes and decarbonised power sources, with support and regulatory and institutional reform provided together. According to METI, the programme was established in August 2025. Regions are selected under three types: industrial complex regeneration, data center clusters, and decarbonised power utilisation.

Which regions were designated as data center cluster GX Strategic Regions?

On 11 September 2026 METI designated 9 regions (10 sites) as the first round of data center cluster GX Strategic Regions: Hokkaido (Ishikari City and Tomakomai City), Akita Prefecture (Akita City), Miyagi Prefecture (Tomiya City), Tochigi Prefecture (Yaita City), Ibaraki Prefecture (Joso City / Tsukuba City), Toyama Prefecture (Nanto City), Kagawa Prefecture (Ayagawa Town / Sakaide City / Marugame City), Fukuoka Prefecture (Kitakyushu City / Nogata City / Kurate Town) and Kagoshima Prefecture (Satsumasendai City).

Can a data center operator apply to become a GX Strategic Region?

For the data center cluster type, the unit of selection is the prefecture. The Cabinet Secretariat's interim report says an application may also be filed jointly with municipalities or private businesses, for example as a consortium. Data center operators take part by joining a local government's plan.

Is there a subsidy for building a data center in a GX Strategic Region?

Locating in a designated region does not by itself bring a subsidy for data center construction. The Cabinet Secretariat's interim report notes that ordinary data center construction is already moving forward on a commercial basis, and limits development support to data centers that contribute to regional dispersal and data centers that use 100% decarbonised power while contributing to the areas hosting decarbonised power sources. The support is finalised through the budget process, so check the latest application guidelines when a call opens.

Do GX Strategic Regions matter for a small data center project?

The data center cluster type aims to create gigawatt-class clusters over roughly ten years, a very different scale from a small project with less than 2 MW of total incoming power. However, grid and telecom infrastructure may be built out earlier in designated regions, so the designation is one piece of information when comparing candidate sites. For any individual project, whatever its size, the power supply is decided through an application to and consultation with the utility.

Will more GX Strategic Regions be designated?

METI says it will continue to refine the business plans of the other promising regions and designate them as GX Strategic Regions in turn, once their plans are sufficiently mature. For the data center cluster type, all nine promising regions selected in April 2026 were designated in the first round. Outlines of each region's plan are to be published later.

Official references

References checked on 20 November 2026. These sources support the specific points above; they do not constitute approval or endorsement of Wallingford or a project. This page is general information, not legal, tax or engineering advice. Laws, programmes and procedures change, and the sources are in Japanese unless noted: confirm the current text with the competent authority and qualified advisers before acting. English names of Japanese programmes and documents are our own translations unless an official English name exists.

  1. Ministry of Economy, Trade and Industry (METI) — GX Strategic Region programme (GX戦略地域制度), policy page, last updated 10 November 2026 (Japanese)
  2. METI press release — First round of GX Strategic Regions designated, 11 September 2026 (Japanese)
  3. METI press release — Promising regions (first-screening regions) selected for the GX Strategic Region programme, 24 April 2026 (Japanese)
  4. METI press release — Call for applications for GX Strategic Regions opens, 23 December 2025 (Japanese)
  5. Cabinet Secretariat, GX Implementation Promotion Office — Creating GX industrial clusters through the GX Strategic Region programme: interim report, 22 December 2025 (PDF, Japanese)
  6. Ministry of Internal Affairs and Communications (MIC) and METI — Public-Private Council on Watt-Bit Collaboration, Report 1.0, June 2025 (PDF, Japanese)
  7. MIC press release — Publication of Report 1.0 of the Public-Private Council on Watt-Bit Collaboration (Japanese)