JAPAN · POLICY · TOKYO

Tokyo's data center guideline:
what developers are asked to do.

On 31 March 2026 the Tokyo Metropolitan Government published its Guideline for Data Centers in Harmony with the City. This page sets out, from the original text, whether it is a new regulation and what a developer needs to do.

By Wallingford Co., Ltd. · Updated

Discuss your project

Key points

On 31 March 2026 the Tokyo Metropolitan Government published its Guideline for Data Centers in Harmony with the City (まちと調和したデータセンターに向けたガイドライン). The guideline does not create a new permit or a size threshold: it organises the existing laws and ordinances and asks developers to share information early, talk with residents and adapt their plans.

  • The guideline itself has no size threshold and no effective date. Every figure comes from an existing system, such as the National Land Use Planning Act or Tokyo's building and environmental ordinances.
  • Filing forms were revised so that the documents state the use is a data center. The aim is for the authorities to learn of construction plans at an early stage.
  • Developers are asked to talk with neighbouring residents early, in addition to the explanations required by law. The guideline gives examples of what to explain.
  • Municipalities may have their own rules. Koto City brought into force, on 1 February 2026, a guidance outline requiring early notice of building plans for large data centers.

This page organises the content from the standpoint of a business planning a data center, based on the text of the guideline and information published by Tokyo and Koto City. The figures and procedures quoted were checked against the Japanese originals on 20 November 2026. The Japanese version of this page is 東京都のデータセンターガイドラインとは.

Overview of the guideline

The Guideline for Data Centers in Harmony with the City was compiled by the Tokyo Metropolitan Government's Bureau of Urban Development. Tokyo describes it as a collection of points for smooth dialogue between developers and residents, and of good examples that developers, residents and local governments can use as a yardstick when coordinating.

Overview of the guideline (per Tokyo's published material)
Nameまちと調和したデータセンターに向けたガイドライン (Guideline for Data Centers in Harmony with the City; our translation)
Published31 March 2026 (the cover reads “March, Reiwa 8, Tokyo Metropolitan Government”)
Responsible bodyTokyo Metropolitan Government, Bureau of Urban Development
PurposeFor developers, to help deliver data centers that coexist with the community; for residents, a reference for dialogue and coordination with developers; for municipalities, a reference for community development
Main contentBasics of data centers; existing rules on location, environmental performance and consideration for surroundings; early gathering and sharing of information; examples of information provided by developers; examples of design measures
Size thresholdNone in the guideline itself (it introduces the thresholds of each separate system)

As trends among data centers located in Tokyo, the guideline mentions medium-sized “retail” facilities used mainly by companies and local governments, and large “hyperscale” facilities used mainly by cloud providers. It contains no description of small facilities or container-type data centers.

Not a new regulation: existing rules organised, plus a yardstick for dialogue

The Tokyo guideline does not create a permit system specific to data centers or an upper limit on the size that can be built. It explains that data centers, like other buildings, must follow the rules and standards set by the various laws and ordinances, and lists them.

What it asks of developers is phrased as an effort. The guideline's closing section asks developers to endeavour to build and operate data centers that coexist with the community, for example by explaining matters of local concern from an early stage and adapting their plans with reference to good examples.

The guideline also notes that it was prepared on the basis of laws and technology as of March 2026 (Reiwa 8), and that the efforts needed for coexistence with the community may change. When planning, check the latest version posted on Tokyo's page.

What developers are asked to do

What the Tokyo guideline asks of developers can be grouped into four things: stating the use in filings, informing the authorities early, explaining to residents, and following up after opening.

1. State “data center” in filings

Tokyo revised its filing forms so that the authorities can learn of data center construction plans at an early stage. Where the intended use of land is a data center, this is stated in the intended-use field of the land transaction notification under the National Land Use Planning Act. Where the use of the building is a data center, this is stated in the environmental performance submissions from fiscal year 2026 (Reiwa 8). The areas that trigger the land transaction notification are explained in Buying or leasing land for a data center in Japan.

2. Inform Tokyo and the municipality early

The guideline asks developers, when they file the National Land Use Planning Act notification after acquiring a large plot or apply under the district decarbonisation planning system, also to inform the community development departments of Tokyo and the municipality concerned, and to consult them on how to communicate with the community and on the plan itself. Tokyo publishes a list of contact points for each municipality.

3. Explain the matters neighbours care about

The guideline says it is important to communicate with neighbouring residents from an early stage, taking opportunities beyond the explanations required by law, and gives examples of the information to provide.

Examples of information to provide, as shown in the guideline
CategoryExamples of what to explain
Outline of the facilityOutline of the facility and why it is being built, the project schedule, the contact point for enquiries
Effects on the surrounding area, and countermeasuresShadow, wind, radio interference and how the building will look; traffic during construction and operation; waste heat, noise, vibration and soot from equipment; backup generators (quantity and location of hazardous materials stored, safety measures, inspection schedule); the security plan
Effects on the global environment, and countermeasuresPower consumption, water use, energy- and resource-saving measures, use of renewable energy, CO2 emissions
Community contribution and other measuresThe greening plan, architectural and exterior design measures (such as reducing the sense of bulk), contribution to the community

The guideline also asks developers to find ways to explain matters that cannot be disclosed for facility security reasons, and to show exterior images and simulations of the surrounding environment as concretely as possible.

4. Keep a contact point after opening, and hand matters over to the operator

The guideline asks developers to hand over reliably to the operating company the matters confirmed through dialogue and coordination before construction, to keep a contact point for residents' enquiries after the facility opens, and to give advance notice when backup generators are inspected. It adds that the developer and the municipality could conclude an agreement so that the developer takes responsibility for delivering what was confirmed.

The existing rules the guideline brings together

The Tokyo guideline introduces the existing systems relevant to building a data center under three headings: location, environmental performance and consideration for surroundings. The table below shows those for which a size or deadline is given. Whether a project is covered depends on the plan and on the decision of the competent office.

Main systems introduced in the guideline (for sites in Tokyo)
SystemWhat the guideline says
Use districts (用途地域)Data centers are in many cases treated as “offices”, and in such cases can be located in use districts other than the exclusively residential ones
Notification under the National Land Use Planning ActRequired, for example, after a transaction of 2,000 m² or more of land in an urbanization promotion area
Development permissionChanges to the division, shape or nature of land with a site area of 500 m² or more, among others
District decarbonisation planning system (地域における脱炭素化に関する計画制度)Covers projects with a total floor area above 50,000 m². The policy is submitted at least 300 days before the building confirmation application or equivalent
Building Environmental Plan system (建築物環境計画書制度)Covers new construction and similar works for buildings with a total floor area of 2,000 m² or more
Greening plan system (緑化計画書制度)A notification, or an application for development permission, is required for development or building on a site of 1,000 m² or more (for private land)
Signs and explanation of building plansUnder the metropolitan ordinance, a sign is posted at least 30 days before the building confirmation application (among other timings), and the plan is explained if neighbouring residents request it
Noise and vibrationRegulated by the Noise Regulation Act, the Vibration Regulation Act and Tokyo's Environmental Preservation Ordinance (環境確保条例). As one example of the standards, noise in residential-type areas is 45–50 dB in the daytime and 40–45 dB at night

The area above which development permission is needed differs by region. The nationwide thresholds are covered in the permits section of Developing an AI data center in Japan: FAQ.

Examples of design measures in the guideline

The Tokyo guideline presents measures for coexistence with the community and consideration for the environment as “example initiatives”. They are not obligations; they are a yardstick for deciding what to adopt in each plan.

  • Noise, vibration and waste heat: careful choice of equipment location and of the position and direction of exhaust outlets, sound-insulating panels and silencers, anti-vibration rubber and mounts, distributing outdoor units, and keeping a distance from adjacent buildings.
  • Backup generators: exhaust purification and fuel control devices to reduce exhaust gas, and use of cogeneration systems or stationary fuel cells.
  • Energy saving: energy-saving technologies such as direct liquid cooling and immersion cooling, renewable energy such as solar panels, and use of the heat produced by the facility.
  • Appearance and greening: colours in harmony with the surroundings, design that reduces the sense of bulk of large windowless walls, building layout that takes shadow into account, and greening beyond the standard.
  • Contribution to the community: open space residents can use, cooperation in charging mobile phones in a disaster, a disaster-preparedness storehouse, and working with local companies.

Fuel for backup generators and the related Fire Service Act procedures are covered in the development FAQ.

Municipal rules: the example of Koto City

Separately from the Tokyo guideline, municipalities may set their own rules. Koto City (江東区, one of Tokyo's 23 special wards) adopted its guidance outline on early notice of building plans for large data centers on 15 December 2025 and brought it into force on 1 February 2026.

Outline of Koto City's guidance outline (per Koto City's published material)
Covered buildingsBuildings in which the floor area used as a data center is the majority of the total floor area, whose height exceeds 10 m and whose total floor area exceeds 3,000 m²
Prior consultation with the cityRequired. The developer informs the city of the outline of the plan promptly
Notice signFor buildings subject to the city's ordinance, posted from 120 days before the day the building confirmation application or equivalent is to be made. For buildings subject to the metropolitan ordinance (total floor area above 10,000 m² and height above 10 m), posted from 90 days before the day the metropolitan sign is to be posted and 120 days before the building confirmation application or equivalent
BriefingHeld within 15 days after the notice sign is posted; a report is submitted within 30 days of the posting date

Koto City explains that the outline strengthens the provisions of its dispute prevention ordinance, and the existing ordinances also apply. When planning in another municipality, check its building and development ordinances, guidance outlines and community development rules at the local government office early in the plan.

Related Tokyo programmes: certification and subsidy

On 31 July 2026 Tokyo announced the creation of a certification programme for data centers that are considerate of the community and the environment (地域や環境に配慮したデータセンター認定制度) and the start of a subsidy for installing server cooling equipment. Certification is for data center facilities installed in Tokyo by businesses engaged in the data center business. Four items are evaluated — energy efficiency (PUE), use of renewable energy, initiatives that give back to the community, and data security — and certification is granted at four levels: Platinum, Gold, Silver and Bronze.

The subsidy is for businesses engaged in the data center business whose annual energy use is 1,500 kilolitres or more in crude oil equivalent, or that operate server rooms of 300 m² or more, and obtaining certification is the main requirement. Application periods and the timing of certification may change, so check the latest guidance on the implementing body's page. For how PUE works, see PUE and Japan's Energy Conservation Act.

What to check for a small data center plan

Because the Tokyo guideline defines no size, it is worth reading even for a small plan with less than 2 MW of total incoming power if the site is in Tokyo. The points below are our own reading of the guideline.

  1. Check whether the municipality of the site has its own rules. As with Koto City's outline, the covered size (height, total floor area) may be set specifically.
  2. Check what the filings must state. For land acquisition and building procedures, ask the receiving office whether the intended-use or use field must state that the facility is a data center.
  3. Prepare explanatory material on noise, waste heat and backup generators at the design stage. Decide the layout of cooling equipment and generators in light of the site boundary and the distance to neighbouring buildings.
  4. Be ready to explain power consumption and your approach to energy saving. The guideline's examples of information to provide include power consumption, water use and energy-saving measures.

On power, the guideline explains that data centers are built after concluding a supply contract with the utility within the range in which stable supply to the area is possible. The application steps are explained in our planning guide.

How Wallingford helps

Wallingford Co., Ltd. supports projects below 2 MW of total incoming power with comparison of candidate sites, support for utility consultations and applications, and comparison of design and construction options. When comparing candidate sites, we include whether the local government has relevant ordinances or guidance outlines among the items to confirm.

This page is a general explanation based on published material, not legal advice on an individual plan. We do not guarantee land availability, power supply, permits or completion dates; confirm whether a procedure is required with the competent office and qualified professionals.

Frequently asked questions

Is Tokyo's data center guideline legally binding?

Tokyo's Guideline for Data Centers in Harmony with the City is reference material for developers, residents and municipalities. The guideline itself sets no new permit and no size threshold. It asks developers to endeavour to explain their plans early and to adapt them, in light of the guideline. Building and environmental obligations are set by the existing laws and ordinances that the guideline summarises.

When does the Tokyo data center guideline take effect?

The Tokyo guideline was published on 31 March 2026. It contains no effective date or transitional provisions of its own. At the same time, filing forms were revised so that land transaction notifications and environmental submissions state that the use is a data center; the statement on building use is required from fiscal year 2026 (Reiwa 8).

Does the guideline apply only above a certain size?

The Tokyo guideline does not define the size of data center it covers. Figures such as areas are set by each separate system the guideline introduces, for example the notification under the National Land Use Planning Act (land transactions of 2,000 m² or more in urbanization promotion areas) and the district decarbonisation planning system, which covers projects with a total floor area above 50,000 m².

Are resident briefings mandatory for data center construction in Tokyo?

Whether explaining a plan to residents is mandatory depends on the size of the building and the ordinances that apply. The Tokyo guideline notes that, under the metropolitan ordinance, a sign showing the building plan must be posted at least 30 days before the building confirmation application (among other timings) and the plan must be explained if neighbouring residents request it; it then asks developers to engage in early dialogue beyond what the law requires. Koto City has its own guidance outline under which it directs developers of large data centers to hold a briefing.

Can a data center be built near housing in Tokyo?

The Tokyo guideline explains that data centers are in many cases treated as offices, and that in such cases they can be located in use districts other than the exclusively residential ones. Actual treatment varies with the content and scale of the building, so confirm the use district of the site and the classification of the building's use with the designated administrative agency (the local government that has building officials).

Do the same steps apply outside Tokyo?

The Tokyo guideline is written with data centers inside Tokyo in mind. Elsewhere, check each local government's ordinances, guidance outlines and community development rules individually. Noise, waste heat, backup generators and appearance are common issues in any region, so the guideline is a useful reference for organising what to explain.

Official references

References checked on 20 November 2026. These sources support the specific points above; they do not constitute approval or endorsement of Wallingford or a project. This page is general information, not legal, tax or engineering advice. Laws, programmes and procedures change, and the sources are in Japanese unless noted: confirm the current text with the competent authority and qualified advisers before acting. English names of Japanese programmes and documents are our own translations unless an official English name exists.

  1. Tokyo Metropolitan Government, Bureau of Urban Development — Guideline for Data Centers in Harmony with the City (まちと調和したデータセンターに向けたガイドライン), March 2026 (PDF, Japanese)
  2. Tokyo Metropolitan Government, Bureau of Urban Development — Data centers in harmony with the city (Japanese)
  3. Tokyo Metropolitan Government press release — Guideline for Data Centers in Harmony with the City published, 31 March 2026 (Japanese)
  4. Koto City — Early notice of building plans for large data centers (Japanese)
  5. Koto City — Guidance outline on early notice of building plans for large data centers, 15 December 2025 (PDF, Japanese)
  6. Tokyo Metropolitan Government press release — Promoting data centers that are considerate of the community and the environment, 31 July 2026 (Japanese)
  7. Cool Net Tokyo (Tokyo Environmental Public Service Corporation) — Certification programme for data centers that are considerate of the community and the environment (Japanese)