PUE is the indicator of a data center's energy efficiency. This page sets out the formula, how PUE relates to incoming power capacity, the targets set by Japan's Energy Conservation Act and the measures in force since April 2026.

By Wallingford Co., Ltd. · Updated

Discuss your project

Key points

PUE (Power Usage Effectiveness) is the total energy consumed by a data center facility divided by the energy consumed by its IT equipment; the lower the value, the higher the energy efficiency. In Japan, the benchmark system under the Energy Conservation Act (省エネ法) sets a target of PUE 1.4 or lower by fiscal year 2030 and a standard of PUE 1.3 or lower for data centers newly built from fiscal year 2029.

  • PUE is calculated from a year of energy. It is a different figure from incoming power capacity, which describes peak power.
  • New measures for data centers took effect in April 2026. There are three: added items in the periodic report and their disclosure, an efficiency standard for new data centers, and extension to tenant-type operators.
  • Whether a business is covered depends on its total energy use. A business using 1,500 kilolitres or more in crude oil equivalent in a fiscal year is a specified business operator.
  • PUE determines how much IT equipment the same incoming power can run. Even for a small project, check it when choosing the cooling method.

This page is a general explanation based on the Agency for Natural Resources and Energy's explanation and the text of the law. The content was checked against the Japanese originals on 20 November 2026. A Japanese fiscal year runs from April to March. The Japanese version of this page is PUEとは.

Definition and formula

PUE is an indicator of a data center's energy efficiency. The Agency for Natural Resources and Energy (ANRE) describes PUE as the total energy consumed by the data center facility divided by the energy consumed by the IT equipment.

PUE = total energy consumed by the data center facility ÷ energy consumed by IT equipment

Total facility energy includes, in addition to IT equipment such as servers and network equipment, the cooling equipment, losses in power receiving, transformation and distribution, uninterruptible power supplies and lighting. The less energy is used by anything other than IT equipment, the closer PUE comes to 1.0.

PUE calculation examples (one year of energy; illustrative figures)
Whole facilityIT equipmentOther than IT (cooling etc.)PUE
16 million kWh10 million kWh6 million kWh1.6
14 million kWh10 million kWh4 million kWh1.4
13 million kWh10 million kWh3 million kWh1.3
12 million kWh10 million kWh2 million kWh1.2

PUE varies with climate, IT utilisation and how the equipment is operated. Just after start-up, when little IT equipment is installed, the fixed consumption of cooling and power distribution is a larger share and PUE tends to be higher.

PUE and incoming power capacity

PUE is a ratio of annual energy, while the incoming power capacity discussed with the utility is peak power. They are different figures, but both relate to the share of the facility's total power that IT equipment can use.

The table below is a simple division showing how the average power available to IT equipment changes with PUE when the facility's average power use is 1,400 kW.

Calculation example for an average facility power use of 1,400 kW
Annual average PUEAverage IT powerAverage non-IT power
1.6875 kW525 kW
1.41,000 kW400 kW
1.3about 1,077 kWabout 323 kW
1.2about 1,167 kWabout 233 kW

Actual incoming power capacity is calculated by the electrical designer, allowing for the cooling load at the summer peak, equipment redundancy and inrush current. Our planning guide explains how incoming power is defined, including the 2,000 kW contract-power boundary between high voltage and extra-high voltage.

The Energy Conservation Act benchmark: PUE 1.4 or lower

Japan's Energy Conservation Act (省エネ法; formally エネルギーの使用の合理化及び非化石エネルギーへの転換等に関する法律) designates businesses whose energy use is above a set scale as specified business operators (特定事業者) and requires them to submit a periodic report and a medium- to long-term plan. A specified business operator is a business that uses 1,500 kilolitres or more of energy in crude oil equivalent in a fiscal year (Order for Enforcement, Article 2). The periodic report and the medium- to long-term plan are due by the end of July each fiscal year (Regulation for Enforcement, Articles 35 and 36).

ANRE explains that, as part of the benchmark system, specified business operators in the data center business are given the target of “a PUE of 1.4 or lower by fiscal year 2030” and are required to calculate and report their PUE.

How much electricity is 1,500 kilolitres?

Electricity use is converted to a crude oil quantity with the factors in Article 4 of the Regulation for Enforcement. Ordinary electricity purchased from a utility is converted at 8.64 gigajoules per 1,000 kWh and 0.0258 kilolitres of crude oil per gigajoule.

Worked example: for a business that uses only purchased electricity, 1,500 kilolitres in crude oil equivalent corresponds to about 6.73 million kWh a year (1,500 ÷ 0.0258 ÷ 8.64 ≈ 6,729 thousand kWh). Averaged over a year (8,760 hours), that is about 770 kW.

Energy use is judged on the total for the whole business, including sites other than data centers. Even a facility with less than 2 MW of incoming power may reach this level on its own if it runs at a high utilisation rate. The conversion factors can be revised, and fuel and heat are added using separate factors, so confirm the determination against the current law and with the competent office.

The three measures in force since April 2026

ANRE explains that new measures, added to the existing rules, took effect in April 2026 to raise the energy efficiency of data centers. There are three main points.

New measures for the data center business (per ANRE's explanation)
MeasureContent
1. Making targets, policies and results visibleFrom the reports submitted in fiscal year 2026, data center items are added to the periodic report and the medium- to long-term plan (actual values such as electricity use, PUE and energy intensity, and future targets). Operators are asked to publish the information on the data centers covered, for example on their own website, by the end of the fiscal year of submission (31 March)
2. Efficiency standard for new data centersData centers newly built from fiscal year 2029 are required to achieve a PUE of 1.3 or lower (from the fiscal year after the point two years after operation starts). An operator that does not meet it is required to prepare and submit a rationalisation plan, and further administrative measures may follow if it does not comply
3. Extension to tenant-type operatorsFrom the reports submitted in fiscal year 2026, the hosting/cloud (tenant) type — bringing one's own IT equipment into space rented from another business — is added to the scope of PUE calculation and reporting and of measures 1 and 2

ANRE's material notes that, of the items added to the periodic report, those subject to disclosure apply only to data centers newly built from fiscal year 2025. Check the report forms and calculation methods in the guidelines posted on ANRE's page.

The three categories of data center covered

The Energy Conservation Act rules divide the data centers covered into three categories according to who owns the IT equipment and the ancillary equipment.

Categories of data center under the Energy Conservation Act (per ANRE's explanation)
CategoryDescription
Housing typeOwns no IT equipment; rents out the space for IT equipment and ancillary equipment such as air conditioning and lighting to other businesses
Hosting/cloud (owner) typeOwns the space, the ancillary equipment and the IT equipment
Hosting/cloud (tenant) typeBrings IT equipment it owns into space rented from another business (a housing-type operator)

A business that owns GPU servers and installs them in an existing data center falls under the tenant type; one that develops its own land and building falls under the owner type. For how to compare colocation (housing) with self-build, see colocation versus self-build.

Checking PUE at the planning stage

PUE is measured once a facility is operating, but an expected value (design PUE) can be checked at the design stage. When comparing quotations, align the following items.

  1. The IT load assumed: PUE differs between a fully loaded facility and one part-way through a phased installation.
  2. Outside air conditions: check that the calculation is an annual one based on the temperature and humidity of the location.
  3. Cooling method: check whether air cooling, direct liquid cooling or immersion cooling is assumed.
  4. Scope of the calculation: check whether power receiving and transformation losses, uninterruptible power supplies, lighting and office areas are included.
  5. Measurement method: decide at the design stage where the energy of the whole facility and of the IT equipment will be metered once operation starts.

PUE may also be evaluated under local government programmes. In July 2026 Tokyo created a certification programme for data centers that are considerate of the community and the environment, which evaluates energy efficiency (PUE) among other items; see Tokyo's data center guideline.

How Wallingford helps

Wallingford Co., Ltd. supports projects below 2 MW of total incoming power with comparison of candidate sites, support for utility consultations and applications, and comparison of design and construction options. When comparing design and construction options, we align the PUE assumptions (IT load, outside air conditions, scope of calculation) so that several proposals can be compared in one table.

Determining whether a business is a specified business operator under the Energy Conservation Act, preparing periodic reports and managing energy are done by the business itself and qualified professionals. This page is a general explanation, not legal advice on an individual plan. We do not guarantee land availability, power supply, permits or completion dates.

Frequently asked questions

What is PUE?

PUE (Power Usage Effectiveness) is the total energy consumed by a data center facility divided by the energy consumed by its IT equipment. The lower the value, the higher the energy efficiency; the theoretical lower limit, with no cooling or power distribution losses at all, is 1.0.

How is PUE calculated?

PUE is calculated as total facility energy divided by IT equipment energy. For example, if a facility uses 14 million kWh in a year, of which IT equipment uses 10 million kWh, the PUE is 1.4. It is calculated from energy over a period, normally one year, not from instantaneous power.

Are PUE 1.4 and PUE 1.3 mandatory in Japan?

The benchmark system under Japan's Energy Conservation Act sets a target for specified business operators in the data center business: a PUE of 1.4 or lower by fiscal year 2030. In addition, data centers newly built from fiscal year 2029 are subject to an efficiency standard of PUE 1.3 or lower, and an operator that does not meet it is required to prepare and submit a rationalisation plan. The rules apply to businesses whose energy use is above a set scale.

Does Japan's Energy Conservation Act apply to small data centers?

Whether a business is a specified business operator under the Energy Conservation Act depends not on the size of a facility but on whether the business as a whole uses 1,500 kilolitres or more of energy in crude oil equivalent in a fiscal year. Calculated from purchased grid electricity alone, 1,500 kilolitres corresponds to about 6.73 million kWh a year, or an average of about 770 kW throughout the year. Even a facility with less than 2 MW of incoming power may be covered if it runs at a high utilisation rate.

Do tenants that place their own servers in someone else's data center have to report PUE?

The Agency for Natural Resources and Energy explains that, from the reports submitted in fiscal year 2026, businesses of the hosting/cloud (tenant) type — those that bring their own IT equipment into space rented from another business — have been added to the scope of PUE calculation and reporting. This applies to businesses that are specified business operators under the Energy Conservation Act.

How can PUE be lowered?

PUE is lowered by reducing the energy used for cooling and the losses in power receiving, transformation and distribution. Methods include cooling without compressors when the outside air is cold, separating cold-air and hot-air aisles, using liquid cooling for high-heat equipment, and choosing high-efficiency transformers and uninterruptible power supplies. PUE tends to worsen when IT utilisation is low, so planning to add equipment in phases also helps.

Official references

References checked on 20 November 2026. These sources support the specific points above; they do not constitute approval or endorsement of Wallingford or a project. This page is general information, not legal, tax or engineering advice. Laws, programmes and procedures change, and the sources are in Japanese unless noted: confirm the current text with the competent authority and qualified advisers before acting. English names of Japanese programmes and documents are our own translations unless an official English name exists.

  1. Agency for Natural Resources and Energy (ANRE) — What to do about the expected growth in data center power demand? A look at the new system for further energy saving, 20 May 2026 (Japanese)
  2. ANRE — Energy Conservation Act rules for factories and business sites: periodic reports, medium- to long-term plans and the benchmark system (Japanese)
  3. Order for Enforcement of the Energy Conservation Act, Article 2 (energy use for designation as a specified business operator) — e-Gov Law Search (Japanese)
  4. Regulation for Enforcement of the Energy Conservation Act, Article 4 (conversion to crude oil equivalent) — e-Gov Law Search (Japanese)
  5. Tokyo Metropolitan Government press release — Promoting data centers that are considerate of the community and the environment, 31 July 2026 (Japanese)
  6. U.S. Department of Energy — Best Practices Guide for Energy-Efficient Data Center Design, revised July 2024 (PDF, English)